Projects : Jayadeva Flyover Reconstruction
Jayadeva Flyover Reconstruction
Posted on
: Aug 08, 2019
Ward
: Jayanagar East
Agency
: Bangalore Metro Rail Corporation Limited
Topic
: City Amenities
Budget
: NA
Estimated time
: 1 year
Project no
: 1
Start date
: 2019-07-15
End date
: 2020-09-15
Description

Per BMRCL’s plans, the flyover has to be demolished to facilitate construction of two new metro lines: R.V. Road to Bommasandra, and Gottigere to Nagawara. An interchange station will be built at Jayadeva junction with six levels of infrastructure, which will include a road-cum-metro rail-flyover for motorists going from Ragigudda to Silk Board.

The BMRCL has set September 2020 as the deadline to complete the work.